Thread: Which of the following is NOT an input to Perform Quality Control?

  1. Default Which of the following is NOT an input to Perform Quality Control?

    Which of the following is NOT an input to Perform Quality Control?

    1.Recommended Defect Repairs
    2.Deliverables
    3.Work Performance Information
    4.Checklists

  2. Default Answer

    Correct answer is Recommended Defect Repairs
    The most important part of the Perform Quality Control process is that your team has to inspect each deliverable in order to verify that it meets its requirements. So what do you need to do that?
    Well, obviously you need the deliverables! And checklists are really useful too, because they help you inspect each deliverable. You need work performance information, because that tells you how well the team is doing the job. But Recommended Defect Repairs aren’t an input - they’re the output!

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
© 2012 - SimpliLearn | All Rights Reserved
купить timberland дешего | Мобильный блог